You need a party wall agreement in England and Wales when you plan work covered by the Party Wall etc. Act 1996, such as cutting into a shared wall, building a new wall on the boundary or digging foundations close to a neighbour’s building. You serve notice on your neighbour, who either consents in writing or goes through a surveyor process that ends in a party wall award.
This guide is based on the government’s Party Wall etc. Act 1996 explanatory booklet and GOV.UK guidance, checked 12 November 2026. The booklet itself says it is a general guide rather than an authoritative reading of the law, so take professional advice on your own project.
01What is a party wall agreement?
“Party wall agreement” is the everyday name for the written outcome of the process the Act sets out. It is either your neighbour’s written consent to your notice or, if there is a dispute, a party wall award drawn up by one or more surveyors.
GOV.UK’s party walls and building work guide says party wall agreements are different from planning permission and building regulations approval. You may need all three, and one does not replace another. If you are still working out whether your extension needs planning permission at all, see our guide to permitted development rights.
02What counts as a party wall?
Paragraph 3 of the booklet describes several types:
- A wall that stands astride the boundary between land belonging to two or more owners, whether it forms part of one building or separates two buildings.
- A wall that stands wholly on one owner’s land but is used by two or more owners to separate their buildings. Only the separating part counts as party.
- A party fence wall: a wall astride the boundary that is not part of a building, such as a garden wall. Wooden fences and hedges are not included.
- A party structure, a wider term covering a wall or floor that separates buildings or parts of buildings with separate staircases or entrances, such as flats.
03What work needs a party wall notice?
The Act covers three kinds of work, each with its own minimum notice period.
| Type of work | Section of the Act | Minimum notice | Examples |
|---|---|---|---|
| Work to an existing party wall or structure | Section 2 | Two months | Cutting in to take a beam, underpinning, inserting a damp proof course, raising the wall |
| New wall on the line of junction (the boundary) | Section 1 | One month | Building a new wall astride or up to the boundary line |
| Excavation within 3 metres | Section 6 | One month | Digging deeper than a neighbour’s foundations within 3 metres of their building |
| Excavation within 6 metres | Section 6 | One month | Digging that would meet a 45 degree line drawn down from the bottom of a neighbour’s foundations |
Work to an existing party wall (section 2)
The booklet’s examples include repairing a party wall, inserting a damp proof course, underpinning its whole thickness, cutting into it to take the bearing of a beam, raising its height, extending it downwards for a basement, and demolishing and rebuilding it.
Minor work such as drilling to put up shelves or replastering may not need notice. The booklet says the key test is whether the work could affect the wall’s structural strength or support. Give at least two months’ notice before the planned start date.
Building on the line of junction (section 1)
If you want to build a new wall on the boundary line, give at least one month’s notice. If you want it to sit astride the boundary and your neighbour does not consent in writing within 14 days, you must build it wholly on your own land and at your own expense.
You can place normal projecting foundations under the neighbour’s land only where necessary, and you must compensate them for any damage. Special foundations need their written consent.
Excavation near a neighbour’s building (section 6)
Notice is needed if you dig within 3 metres of any part of a neighbour’s building or structure and any part of your excavation goes deeper than their foundations. It is also needed within 6 metres where your excavation would meet a line drawn downwards at 45 degrees from the bottom of their foundations.
Give at least one month’s notice, say whether you plan to strengthen or safeguard their foundations, and include plans and sections.
04What should a party wall notice include?
There is no set form, but paragraph 8 of the booklet says a notice should include:
- the name and address of the building owner, naming all joint owners;
- the address of the building to be worked on;
- a full description of the proposed work, with plans where helpful (they are required for excavation);
- the proposed start date, which must fall after the notice period ends.
Date the notice and state clearly that it is a notice under the Act. The government’s party wall guidance page publishes example letters for each type of notice and acknowledgement, and notices can be sent electronically if your neighbour agrees.
A notice is only valid for a year, so do not serve it too long before you plan to start. Good drawings help here too; see why good extension drawings decide whether your build goes smoothly.
05How can a neighbour respond to a party wall notice?
Under paragraph 10 of the booklet, a neighbour who receives a notice can:
- Consent in writing. The work can go ahead as described. Agreeing does not take away the neighbour’s rights under the Act, and you still have your duties.
- Refuse. A dispute arises and the surveyor process begins.
- Serve a counter notice. For work to an existing party wall, the neighbour can, within one month, ask for additional or modified work. You then have 14 days to respond, or a dispute is deemed to have arisen.
- Do nothing. See the next section.
A neighbour cannot stop you exercising the rights the Act gives you. The booklet says they “may be able to influence how and at what times the work is done”.
06What happens if my neighbour doesn’t respond?
For work to an existing party wall or for excavation, if your neighbour has not responded within 14 days of being served, a dispute is deemed to have arisen and you move to the surveyor process.
For a new wall on the line of junction, silence means you can only build the wall at your own expense, as an external wall wholly within your own land.
If your neighbour then refuses or fails to appoint a surveyor, you cannot use an agreed surveyor. Under section 10(4) of the Act, if they neglect to appoint one for ten days after you serve a request, you can make the appointment on their behalf.
07Do I need a party wall surveyor?
Only if there is a dispute. If your neighbour consents in writing, you do not need surveyors. If not, paragraph 12 of the booklet sets out two options:
| Option | How it works | Points to note |
|---|---|---|
| Agreed surveyor | Both owners appoint one surveyor, who draws up the award | Only possible if both owners agree on the appointment |
| Two surveyors | Each owner appoints their own surveyor and the two draw up the award together | The two select a third surveyor, called in only if they cannot agree or an owner or surveyor asks |
Surveyors must consider the interests of both owners and draw up the award impartially. Anyone who is not a party to the work can act as a surveyor, but an owner cannot act for themselves.
Our articles on what happens if you don’t appoint a party wall surveyor and who pays for the party wall surveyor answer common follow up questions.
08What is a party wall award?
An award is a document that sets out the work to be done, when and how it will be carried out, and any additional protection needed. It often includes a record of the condition of the neighbour’s property before work starts.
The booklet says the award “is final and binding unless it is rescinded or modified by a county court on appeal”. Each owner has 14 days from service of the award to appeal to the county court.
09Who pays for a party wall agreement?
Usually the building owner. The booklet says the building owner will normally pay all the costs of drawing up the award, including the neighbour’s surveyor’s fees, where the work is solely for their benefit.
Where work is needed because of a defect or lack of repair, costs may be shared according to use and responsibility. Surveyors’ fees are set by negotiation; the Act provides for reasonable costs, and you can ask for a breakdown.
A neighbour can also ask, before work starts, for security for expenses, such as money, a bond or insurance, so they could restore their property if you stopped work part way. The booklet says this is usually reserved for particularly intrusive or complex works.
10What are my duties once work starts?
GOV.UK’s guidance on when works begin says you must avoid causing unnecessary inconvenience, protect your neighbour’s property from damage caused by the works, and fix or pay for any damage that is caused.
Your neighbour must let surveyors and workers in during usual working hours to carry out the works, and you must give 14 days’ notice except in an emergency. Access can be harder than it looks on narrow plots; see the access challenges of renovating a Victorian terrace.
11What if building work starts without a party wall notice?
The Act has no enforcement procedure of its own for a failure to serve notice. However, the booklet says an adjoining owner can seek to stop the work through a court injunction, which is why it pays to serve notice properly at the start.
Build the notice period into your timetable alongside your other approvals. Our guide to loft conversion costs and our single storey extension ideas can help you plan the wider project.
12Does the Party Wall Act apply in Wales, Scotland and Northern Ireland?
The Act applies throughout England and Wales, so the process in this guide is the same in Wales. The booklet states that it does not apply to Scotland or Northern Ireland, so take local legal advice there before working on a shared wall.
Wherever you are, planning permission and building regulations are separate matters, and your local planning and building control authorities can tell you what else your project needs.